[DUB] Power Maintenance
Scheduled Maintenance Report for dub
Completed
CloudSigma would like to inform you that the annual black building test was performed. During the tests, the electricity in our facility was stopped, in order to test that the generators kick in correctly.

IMPACT:
There was no impact on already existing/running customers’ virtual machines, hosts, network accessibility, and/or any other running services.
Posted Nov 11, 2023 - 12:41 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 11, 2023 - 09:00 UTC
Scheduled
CloudSigma would like to inform you of an upcoming annual black building test will be performed. During the tests, the electricity in our facility will be stopped, in order to test that the generators kick-in correctly.

IMPACT:
There will be no impact on already existing/running customers’ virtual machines, hosts, network accessibility and/or any other running services. All power is already provided through the UPSs, so there is no risk of an outage. If the generators fail to act correctly, then power is restored before UPSs run out.
Posted Nov 04, 2023 - 00:26 UTC
This scheduled maintenance affected: Dublin Cloud.